Road projects commonly cover large areas and may extend for several kilometres. Before measuring or pricing any item, a quantity surveyor must understand where the relevant drawing area sits within the overall project. This article explains a practical sequence for reading a road construction drawing, using an actual project example for a road tunnel beneath an airport runway.
A drawing sheet may show only a small part of a much larger road network. Starting measurement immediately from a detailed plan can create uncertainty about the start point, end point and exact project location.
The key plan provides the broadest view of the project. It helps the reader identify:
In the example, the key plan shows an airport environment with runways, buildings and roads. A highlighted red line identifies the portion being considered. This portion relates to a tunnel: the runway is above it and the tunnel runs below.
After identifying the general project area, move to the location plan. The location plan is a zoomed-in view of the relevant section identified on the key plan.
It should be used to establish:
This approach breaks the information down from a large-scale project view to a more focused work area. It is particularly useful during quantity take-off because it helps prevent omissions, duplication and measurement of the wrong location.
Once the location is clear, review the overall plan for the road arrangement. In this example, the road has two carriageways:
The overall plan gives context to the detailed symbols, markings and references shown on the sheet. It also helps the quantity surveyor establish whether an item applies to one carriageway, both carriageways, a specific lane or only a localised area.
The title block is one of the most important places to check before interpreting or quantifying a drawing. It identifies the discipline, work package, drawing title and drawing status.
The discipline in this example is Civil and Site Work. Road works fall within civil works and are carried out as site works within the project.
The work package is Road Works according to BOQ. The BOQ work package helps connect the construction information shown on the drawing with the relevant bill items for measurement, pricing and valuation.
The title is stated as Orba Road Tunnel One Area Road Ceramic Marking Plan and Details.
The title indicates that the drawing is concerned with the arrangement and details of ceramic road markers. A title should always be checked because it tells the reader why the drawing was produced and what information it is intended to communicate.
The example is identified as a shop drawing. The transcript describes three drawing stages:
For measurement and construction review, it is essential to confirm the status of the drawing being used. The work in this example is stated to be executed based on the shop drawing.
The drawing concerns ceramic road markers, described in the lesson as yellow signs or markers installed at the side of the road. Their purpose is to provide road guidance and assist traffic management by helping vehicles identify road lines and spacing.
These markers are also referred to in the lesson as cat eyes. The plan communicates the arrangement and spacing at which the markers are to be installed along the road.
After reviewing the overall plan, examine the details shown on the drawing. Details explain the symbols and marker references used in the plan.
Examples mentioned include:
These references identify different marker types or colours. The same reference names can be traced in the BOQ when reviewing the related work items. This link between the drawing and BOQ is important for accurate quantity take-off.
Use the following sequence whenever reviewing a road construction drawing or preparing quantities: