The Statement at Completion under FIDIC Clause 14.10

Asad Ali

Wed, 25 Nov 2026

The Statement at Completion under FIDIC Clause 14.10

FIDIC contracts

The Statement at completion under FIDIC Clause 14.10

Within 84 days of completion the contractor must set out everything it is owed. Leave a claim out and Clause 14.14 may stop you recovering it later

When the works are taken over, the monthly payment cycle starts to give way to the final account. The first formal step is the Statement at completion under Sub-Clause 14.10. It looks like just another payment application, but it has a sting in the tail: anything the contractor fails to include may be lost for good.

This article follows the FIDIC Red Book 2017 (second edition).

What Clause 14.10 says

Within 84 days after the Date of Completion of the Works, as stated in the Taking-Over Certificate, the contractor must submit to the Engineer a Statement at completion, with supporting documents, in the same way as a monthly Statement under Clause 14.3. It must show:

  1. The value of all work done in accordance with the contract up to the Date of Completion.
  2. Any further sums the contractor considers due at the Date of Completion.
  3. An estimate of any other amounts the contractor considers have or will become due after the Date of Completion, under the contract or otherwise, shown separately. This includes claims already notified, matters referred to the DAAB, and any Notice of Dissatisfaction.

The Engineer then certifies the Statement in the same way as an interim payment, under Clause 14.6.

Why it matters: Clause 14.14

Sub-Clause 14.14, Cessation of Employer's Liability, is the reason to take this Statement seriously. In broad terms, the Employer is not liable for any matter arising before the Taking-Over Certificate unless the contractor included an amount for it in the Statement at completion, and in the Final Statement. There are limited exceptions, but the safe rule is simple: if it is not in the Statement, assume you cannot recover it.

What to include: a checklist

ItemWhere it goesEvidence
Remeasured BOQ work(a) Value of work doneFinal measurement sheets and as-built drawings
Agreed variations(a) Value of work doneVariation instructions and agreed valuations
Unpaid certified sums(b) Further sums duePayment certificates and bank records
Financing charges(b) Further sums due14.8 calculation and rate evidence
Retention still held(b) Further sums dueRetention register
Unagreed variations(c) Estimated amountsContractor's valuation and correspondence
Notified claims, including EOT costs(c) Estimated amountsClause 20 notices and fully detailed claims
DAAB referrals and disputes(c) Estimated amountsReferral, decision, Notice of Dissatisfaction

Practical tips for the quantity surveyor

  • Start before taking-over. Build a live claims and variations register during the project so the Statement at completion is a summary, not a research project.
  • Diary the 84 days from the Date of Completion stated in the Taking-Over Certificate, not from the date you received it.
  • Over-include rather than under-include. Give an honest estimate for every open matter. An estimate can be revised in the Final Statement; an omission may be fatal.
  • Separate estimates clearly. FIDIC requires estimated amounts to be shown separately from the value of work and sums due.
  • Reconcile with the Employer's records. Agree as much as possible now, so the Final Statement has fewer disputes.

Frequently asked questions

When is the Statement at completion due under FIDIC 2017?

Within 84 days after the Date of Completion of the Works stated in the Taking-Over Certificate.

Is the Statement at completion the final account?

No. It is an interim step. The final account is settled through the Final Statement under Clause 14.11, after the Performance Certificate.

What happens if a claim is left out?

Under Clause 14.14 the Employer may cease to be liable for matters arising before taking-over that were not included in the Statement at completion and the Final Statement. Always include every open matter, with an estimate if the value is not yet known.

Conclusion

The Statement at completion is the contractor's chance to put every pound, dollar or riyal it believes it is owed on the record. Prepare it from a register you have kept all project long, and include every open claim. The final step comes next: the Final Statement under Clause 14.11.