The Final Statement under FIDIC Clause 14.11: Closing the Account
Wed, 25 Nov 2026
Practical guides, tutorials and real-world insights for quantity surveyors and construction professionals.
FIDIC contracts
Within 84 days of completion the contractor must set out everything it is owed. Leave a claim out and Clause 14.14 may stop you recovering it later
When the works are taken over, the monthly payment cycle starts to give way to the final account. The first formal step is the Statement at completion under Sub-Clause 14.10. It looks like just another payment application, but it has a sting in the tail: anything the contractor fails to include may be lost for good.
This article follows the FIDIC Red Book 2017 (second edition).
Within 84 days after the Date of Completion of the Works, as stated in the Taking-Over Certificate, the contractor must submit to the Engineer a Statement at completion, with supporting documents, in the same way as a monthly Statement under Clause 14.3. It must show:
The Engineer then certifies the Statement in the same way as an interim payment, under Clause 14.6.
Sub-Clause 14.14, Cessation of Employer's Liability, is the reason to take this Statement seriously. In broad terms, the Employer is not liable for any matter arising before the Taking-Over Certificate unless the contractor included an amount for it in the Statement at completion, and in the Final Statement. There are limited exceptions, but the safe rule is simple: if it is not in the Statement, assume you cannot recover it.
| Item | Where it goes | Evidence |
|---|---|---|
| Remeasured BOQ work | (a) Value of work done | Final measurement sheets and as-built drawings |
| Agreed variations | (a) Value of work done | Variation instructions and agreed valuations |
| Unpaid certified sums | (b) Further sums due | Payment certificates and bank records |
| Financing charges | (b) Further sums due | 14.8 calculation and rate evidence |
| Retention still held | (b) Further sums due | Retention register |
| Unagreed variations | (c) Estimated amounts | Contractor's valuation and correspondence |
| Notified claims, including EOT costs | (c) Estimated amounts | Clause 20 notices and fully detailed claims |
| DAAB referrals and disputes | (c) Estimated amounts | Referral, decision, Notice of Dissatisfaction |
Within 84 days after the Date of Completion of the Works stated in the Taking-Over Certificate.
No. It is an interim step. The final account is settled through the Final Statement under Clause 14.11, after the Performance Certificate.
Under Clause 14.14 the Employer may cease to be liable for matters arising before taking-over that were not included in the Statement at completion and the Final Statement. Always include every open matter, with an estimate if the value is not yet known.
The Statement at completion is the contractor's chance to put every pound, dollar or riyal it believes it is owed on the record. Prepare it from a register you have kept all project long, and include every open claim. The final step comes next: the Final Statement under Clause 14.11.