The Final Statement under FIDIC Clause 14.11: Closing the Account
Wed, 25 Nov 2026
Practical guides, tutorials and real-world insights for quantity surveyors and construction professionals.
FIDIC contracts
Retention comes back in two halves: one at taking-over, one after the Defects Notification Period. Under the 2017 Red Book the contractor has to ask for it, so do not leave money on the table
Retention money is the part of each interim payment the Employer holds back as security for the contractor completing the works and fixing defects. On a large project it adds up quickly, and it is often the contractor's profit sitting in someone else's account. Sub-Clause 14.9 sets out when and how it comes back.
This article follows the FIDIC Red Book 2017 (second edition), the same edition as the rest of this series.
Each month, the contractor's Statement under Clause 14.3 shows a deduction for retention: the percentage stated in the Contract Data, applied to the value of work, until the limit of retention money is reached. That accumulated sum is the "Retention Money" that Clause 14.9 releases.
| Stage | Trigger | Amount released |
|---|---|---|
| First release | Taking-Over Certificate issued for the Works | First half of the Retention Money |
| First release (Section or Part) | Taking-Over Certificate for a Section or Part | The relevant proportion of the first half |
| Second release | Expiry of the latest Defects Notification Period | The balance of the Retention Money |
| Second release (Section) | Expiry of the DNP for that Section | The relevant proportion of the second half |
The important change from the 1999 edition is who acts. Under the 2017 Red Book, after the trigger event the contractor includes the retention amount in a Statement, and the Engineer then certifies it in the normal way. If the contractor forgets to apply, the money simply stays with the Employer.
A road contract has an Accepted Contract Amount of $10 million. The Contract Data sets retention at 10% of each interim payment, up to a limit of 5% of the Accepted Contract Amount.
| Step | Calculation | Amount |
|---|---|---|
| Retention limit | 5% × $10,000,000 | $500,000 |
| Limit reached | When certified work reaches $5,000,000 | $500,000 held |
| Taking-over | First half included in the next Statement | $250,000 |
| DNP expires | Balance included in a Statement | $250,000 |
Once included in a Statement, each release follows the normal timetable: the Engineer certifies within 28 days under Clause 14.6, and the Employer pays within 56 days of the Engineer receiving the Statement under Clause 14.7.
Some contracts let the contractor replace cash retention with a bank guarantee, usually once the first half has been released. FIDIC publishes an example form of retention money guarantee for this purpose, but it only applies if your Particular Conditions provide for it. Check before you rely on it, and compare the bank's fee with the cash-flow benefit.
After the Taking-Over Certificate for the Works is issued. The contractor includes the first half in a Statement, and the Engineer certifies it for payment.
After the latest of the Defects Notification Periods has expired. The contractor includes the balance in a Statement.
Under 1999, the Engineer certified retention release when the trigger occurred, and a Section release was set at 40% of the Section's proportion. Under 2017, the contractor must include the release in a Statement, using the relevant proportion for Sections.
Retention is the contractor's money, held on trust for good performance. Track it, diary the triggers and apply on time. Next in this series: the Statement at completion under Clause 14.10, where the final account really begins.