Release of Retention Money under FIDIC: Clause 14.9 Explained

Asad Ali

Wed, 25 Nov 2026

Release of Retention Money under FIDIC: Clause 14.9 Explained

FIDIC contracts

Release of retention money under FIDIC: Clause 14.9 explained

Retention comes back in two halves: one at taking-over, one after the Defects Notification Period. Under the 2017 Red Book the contractor has to ask for it, so do not leave money on the table

Retention money is the part of each interim payment the Employer holds back as security for the contractor completing the works and fixing defects. On a large project it adds up quickly, and it is often the contractor's profit sitting in someone else's account. Sub-Clause 14.9 sets out when and how it comes back.

This article follows the FIDIC Red Book 2017 (second edition), the same edition as the rest of this series.

How retention builds up

Each month, the contractor's Statement under Clause 14.3 shows a deduction for retention: the percentage stated in the Contract Data, applied to the value of work, until the limit of retention money is reached. That accumulated sum is the "Retention Money" that Clause 14.9 releases.

What Clause 14.9 says

StageTriggerAmount released
First releaseTaking-Over Certificate issued for the WorksFirst half of the Retention Money
First release (Section or Part)Taking-Over Certificate for a Section or PartThe relevant proportion of the first half
Second releaseExpiry of the latest Defects Notification PeriodThe balance of the Retention Money
Second release (Section)Expiry of the DNP for that SectionThe relevant proportion of the second half

The important change from the 1999 edition is who acts. Under the 2017 Red Book, after the trigger event the contractor includes the retention amount in a Statement, and the Engineer then certifies it in the normal way. If the contractor forgets to apply, the money simply stays with the Employer.

A worked example

A road contract has an Accepted Contract Amount of $10 million. The Contract Data sets retention at 10% of each interim payment, up to a limit of 5% of the Accepted Contract Amount.

StepCalculationAmount
Retention limit5% × $10,000,000$500,000
Limit reachedWhen certified work reaches $5,000,000$500,000 held
Taking-overFirst half included in the next Statement$250,000
DNP expiresBalance included in a Statement$250,000

Once included in a Statement, each release follows the normal timetable: the Engineer certifies within 28 days under Clause 14.6, and the Employer pays within 56 days of the Engineer receiving the Statement under Clause 14.7.

Retention money guarantees

Some contracts let the contractor replace cash retention with a bank guarantee, usually once the first half has been released. FIDIC publishes an example form of retention money guarantee for this purpose, but it only applies if your Particular Conditions provide for it. Check before you rely on it, and compare the bank's fee with the cash-flow benefit.

What the quantity surveyor should do

  • Keep a running retention register by month, showing the amount held, the limit and any Sections.
  • Diary the triggers: the Taking-Over Certificate for each Section and the expiry of each Defects Notification Period.
  • Apply promptly. Include the release in the first Statement after each trigger, with a copy of the certificate.
  • Watch for withholding. If the Engineer holds back part of a release for outstanding work, ask for the work and its estimated cost to be identified in writing.
  • Pass it down. Check that subcontract retention releases line up with the main contract, so you are not paying out before you are paid.

Frequently asked questions

When is the first half of retention released under FIDIC 2017?

After the Taking-Over Certificate for the Works is issued. The contractor includes the first half in a Statement, and the Engineer certifies it for payment.

When is the second half released?

After the latest of the Defects Notification Periods has expired. The contractor includes the balance in a Statement.

What changed from the 1999 Red Book?

Under 1999, the Engineer certified retention release when the trigger occurred, and a Section release was set at 40% of the Section's proportion. Under 2017, the contractor must include the release in a Statement, using the relevant proportion for Sections.

Conclusion

Retention is the contractor's money, held on trust for good performance. Track it, diary the triggers and apply on time. Next in this series: the Statement at completion under Clause 14.10, where the final account really begins.

For practical training on payment applications and final accounts, see Advanced Quantity Surveying: Payments under FIDIC and NEC Contracts.