Under the 2017 Red Book the payment clock starts when the Engineer receives your Statement, not when the certificate is issued. Here is how the deadlines work, with a worked timeline
Clause 14.7 is the point in the FIDIC payment cycle where money finally moves. The contractor has applied under Clause 14.3, the Engineer has certified under Clause 14.6, and now the Employer must pay the certified amount within a fixed period.
The detail that catches people out is when that period starts. For ordinary monthly payments it runs from the date the Engineer receives the contractor's Statement, not from the date the Interim Payment Certificate (IPC) is issued. A slow Engineer does not buy the Employer extra time.
This article follows the FIDIC Red Book 2017 (second edition). The periods below are the defaults in the General Conditions; your Contract Data or Particular Conditions may change them, so always check those first.
The Employer must pay the contractor:
| Payment | The clock starts when… | Default period |
|---|---|---|
| Advance payment | The Employer receives the Advance Payment Certificate | 21 days |
| Interim payment (monthly IPC) | The Engineer receives the Statement and supporting documents | 56 days |
| IPC for a Partially Agreed Final Statement | The Employer receives that IPC | 28 days |
| Final Payment Certificate | The Employer receives the Final Payment Certificate | 56 days |
Defaults under the FIDIC Red Book 2017 General Conditions. Check the Contract Data for project-specific periods.
Payment is made in the currencies set out in the contract (see Sub-Clause 14.15) into the bank account the contractor has nominated.
The Engineer has 28 days from receiving the Statement to issue the IPC. The Employer has 56 days from that same receipt date to pay. If the Engineer uses the full 28 days, the Employer is left with roughly 28 days to process the payment.
If the Engineer certifies late, the payment date does not move. Sub-Clause 14.8 says the period of delay starts on the date for payment in 14.7, whenever the IPC was issued. That protects the contractor's cash flow from slow certification.
Suppose the Engineer receives the contractor's monthly Statement, with full supporting documents, on 30 June.
| Step | Rule | Date |
|---|---|---|
| Statement received | Clause 14.3 | 30 June |
| IPC due | 28 days after receipt (14.6) | 28 July |
| Payment due | 56 days after receipt (14.7) | 25 August |
| Financing charges start | Any day after 25 August (14.8) | 26 August onwards |
Notice how much depends on the first date. If the supporting documents are incomplete and the Engineer asks for more information, the receipt date, and with it the whole timeline, can slip.
No. For interim payments under the 2017 Red Book, the 56 days run from the date the Engineer receives the Statement and supporting documents. The IPC date does not change the payment deadline.
The Employer's obligation is to pay the amount certified. Deductions for the Employer's own claims should go through the claims procedure in Clause 20 and be agreed or determined by the Engineer first, rather than simply being withheld from a certified payment.
Yes. Many projects change the payment periods in the Contract Data or Particular Conditions, especially on public-sector work. The contract you signed always takes priority over the default General Conditions.
Clause 14.7 is short, but it sets the rhythm of the contractor's cash flow. Treat the Statement receipt date as the most important date of the month, keep evidence of it, and track the 28-day and 56-day deadlines. Next in this series: what happens when the Employer pays late, under Clause 14.8.