When Must the Employer Pay? FIDIC Clause 14.7 Explained

Asad Ali

Wed, 25 Nov 2026

When Must the Employer Pay? FIDIC Clause 14.7 Explained

FIDIC contracts

When must the employer pay? FIDIC Clause 14.7 explained

Under the 2017 Red Book the payment clock starts when the Engineer receives your Statement, not when the certificate is issued. Here is how the deadlines work, with a worked timeline

Clause 14.7 is the point in the FIDIC payment cycle where money finally moves. The contractor has applied under Clause 14.3, the Engineer has certified under Clause 14.6, and now the Employer must pay the certified amount within a fixed period.

The detail that catches people out is when that period starts. For ordinary monthly payments it runs from the date the Engineer receives the contractor's Statement, not from the date the Interim Payment Certificate (IPC) is issued. A slow Engineer does not buy the Employer extra time.

This article follows the FIDIC Red Book 2017 (second edition). The periods below are the defaults in the General Conditions; your Contract Data or Particular Conditions may change them, so always check those first.

What Clause 14.7 says

The Employer must pay the contractor:

PaymentThe clock starts when…Default period
Advance paymentThe Employer receives the Advance Payment Certificate21 days
Interim payment (monthly IPC)The Engineer receives the Statement and supporting documents56 days
IPC for a Partially Agreed Final StatementThe Employer receives that IPC28 days
Final Payment CertificateThe Employer receives the Final Payment Certificate56 days

Defaults under the FIDIC Red Book 2017 General Conditions. Check the Contract Data for project-specific periods.

Payment is made in the currencies set out in the contract (see Sub-Clause 14.15) into the bank account the contractor has nominated.

Why the 56 days run from the Statement

The Engineer has 28 days from receiving the Statement to issue the IPC. The Employer has 56 days from that same receipt date to pay. If the Engineer uses the full 28 days, the Employer is left with roughly 28 days to process the payment.

If the Engineer certifies late, the payment date does not move. Sub-Clause 14.8 says the period of delay starts on the date for payment in 14.7, whenever the IPC was issued. That protects the contractor's cash flow from slow certification.

A worked timeline

Suppose the Engineer receives the contractor's monthly Statement, with full supporting documents, on 30 June.

StepRuleDate
Statement receivedClause 14.330 June
IPC due28 days after receipt (14.6)28 July
Payment due56 days after receipt (14.7)25 August
Financing charges startAny day after 25 August (14.8)26 August onwards

Notice how much depends on the first date. If the supporting documents are incomplete and the Engineer asks for more information, the receipt date, and with it the whole timeline, can slip.

What the quantity surveyor should do

  • Get the receipt date on record. Submit through the agreed channel and keep the Engineer's acknowledgement. Every later deadline is counted from it.
  • Submit complete supporting documents. Measurement sheets, progress report, variation records and invoices for materials on site. Gaps give the Engineer a reason to ask for more and delay the clock.
  • Diary day 28 and day 56. If no IPC has arrived by day 28, chase the Engineer in writing. If no payment has arrived by day 56, the Employer is late.
  • Reconcile the payment against the IPC. Check retention, advance payment recovery and any other deductions line by line before you close the month.
  • Know the next steps. Late payment triggers financing charges under 14.8. Under Sub-Clause 16.1 the contractor may also suspend or slow work after giving at least 21 days' Notice.

Frequently asked questions

Does the 56-day period start from the IPC date?

No. For interim payments under the 2017 Red Book, the 56 days run from the date the Engineer receives the Statement and supporting documents. The IPC date does not change the payment deadline.

Can the Employer pay less than the certified amount?

The Employer's obligation is to pay the amount certified. Deductions for the Employer's own claims should go through the claims procedure in Clause 20 and be agreed or determined by the Engineer first, rather than simply being withheld from a certified payment.

Can these periods be different on my project?

Yes. Many projects change the payment periods in the Contract Data or Particular Conditions, especially on public-sector work. The contract you signed always takes priority over the default General Conditions.

Conclusion

Clause 14.7 is short, but it sets the rhythm of the contractor's cash flow. Treat the Statement receipt date as the most important date of the month, keep evidence of it, and track the 28-day and 56-day deadlines. Next in this series: what happens when the Employer pays late, under Clause 14.8.