The Final Statement under FIDIC Clause 14.11: Closing the Account
Wed, 25 Nov 2026
Practical guides, tutorials and real-world insights for quantity surveyors and construction professionals.
FIDIC contracts
If the Employer misses the payment date, the contractor is entitled to financing charges compounded monthly. Here is the rate, the calculation and how to claim it
Late payment is one of the most common problems on construction projects, and one of the most damaging for a contractor's cash flow. FIDIC deals with it in Sub-Clause 14.8, Delayed Payment. In short: if the contractor is not paid by the date set in Clause 14.7, it is entitled to financing charges on the unpaid amount, compounded monthly, for the whole period of delay.
This article follows the FIDIC Red Book 2017 (second edition). Check your Contract Data and Particular Conditions, because the rate is often changed there.
Unless the Contract Data states otherwise, the annual rate is three percentage points above:
Many contracts replace this with a fixed rate or a named benchmark in the Contract Data. Whatever the source, keep evidence of the published rate for each month you claim.
An Interim Payment Certificate for $500,000 was due to be paid on 25 August. The Employer pays it on 24 October, two months late. The prime lending rate for the currency is 8%, so the financing rate is 8% plus three percentage points: 11% a year.
| Item | Calculation | Result |
|---|---|---|
| Annual rate | 8% prime + 3 points | 11% |
| Monthly rate | 11 ÷ 12 | 0.9167% a month |
| Month 1 charge | $500,000 × 0.9167% | $4,583 |
| Month 2 charge | $504,583 × 0.9167% | $4,625 |
| Total financing charges | Compounded over two months | $9,208 |
Illustrative figures. For part months, agree a daily pro-rata method with the Engineer and use it consistently.
Financing charges compensate for delay, but they do not fix a cash-flow crisis. FIDIC gives the contractor stronger remedies for serious non-payment:
Both steps are serious and the Notice requirements are strict. Take contractual or legal advice before using them.
Under the Red Book 2017, the contractor is entitled to financing charges without a formal claim notice or certification. In practice, include the amount and calculation in the next Statement so the Engineer can certify it.
From the payment date under Clause 14.7. Sub-Clause 14.8 says the period starts on that date irrespective of when the Interim Payment Certificate was issued.
Compound. FIDIC states the charges are compounded monthly on the amount unpaid.
Clause 14.8 turns late payment into a cost for the Employer. Calculate the charges accurately, claim them in every Statement while payment is late, and keep a clear record of due dates and receipt dates. Next in this series: how retention money is released under Clause 14.9.
For practical training on payment applications, certificates and claims, see Advanced Quantity Surveying: Payments under FIDIC and NEC Contracts.
Wed, 25 Nov 2026
Wed, 25 Nov 2026
Wed, 25 Nov 2026
Leave a comment