Late Payment under FIDIC: How Financing Charges Work (Clause 14.8)

Asad Ali

Wed, 25 Nov 2026

Late Payment under FIDIC: How Financing Charges Work (Clause 14.8)

FIDIC contracts

Late payment under FIDIC: how financing charges work (Clause 14.8)

If the Employer misses the payment date, the contractor is entitled to financing charges compounded monthly. Here is the rate, the calculation and how to claim it

Late payment is one of the most common problems on construction projects, and one of the most damaging for a contractor's cash flow. FIDIC deals with it in Sub-Clause 14.8, Delayed Payment. In short: if the contractor is not paid by the date set in Clause 14.7, it is entitled to financing charges on the unpaid amount, compounded monthly, for the whole period of delay.

This article follows the FIDIC Red Book 2017 (second edition). Check your Contract Data and Particular Conditions, because the rate is often changed there.

What Clause 14.8 says

  • Entitlement: if the contractor does not receive payment in accordance with 14.7, it is entitled to financing charges on the amount unpaid during the period of delay.
  • Compounding: the charges are compounded monthly.
  • Start date: the period of delay starts on the date for payment under 14.7, irrespective of when the Interim Payment Certificate was issued. A late certificate does not delay the start.
  • No formal claim needed: the contractor is entitled to these charges without having to give a formal claim notice or wait for certification, and without losing any other rights or remedies.

What rate applies?

Unless the Contract Data states otherwise, the annual rate is three percentage points above:

  1. the average bank short-term lending rate to prime borrowers for the currency of payment, at the place of payment; or, if there is no such rate there,
  2. the same rate in the country of the currency of payment; or, failing that,
  3. the appropriate rate fixed by the law of the country of the currency of payment.

Many contracts replace this with a fixed rate or a named benchmark in the Contract Data. Whatever the source, keep evidence of the published rate for each month you claim.

A worked example

An Interim Payment Certificate for $500,000 was due to be paid on 25 August. The Employer pays it on 24 October, two months late. The prime lending rate for the currency is 8%, so the financing rate is 8% plus three percentage points: 11% a year.

ItemCalculationResult
Annual rate8% prime + 3 points11%
Monthly rate11 ÷ 120.9167% a month
Month 1 charge$500,000 × 0.9167%$4,583
Month 2 charge$504,583 × 0.9167%$4,625
Total financing chargesCompounded over two months$9,208

Illustrative figures. For part months, agree a daily pro-rata method with the Engineer and use it consistently.

How to claim the charges

  • Add a separate line to your next Statement under Clause 14.3, titled "Financing charges under Sub-Clause 14.8".
  • Attach the calculation: the certificate, the due date, the date actually paid, the rate source for each month and the compounding.
  • Keep the evidence: bank statements showing the receipt date, and the published lending rate.
  • Track part payments: if the Employer pays part of a certificate, charges run only on the unpaid balance from that date.

When interest is not enough

Financing charges compensate for delay, but they do not fix a cash-flow crisis. FIDIC gives the contractor stronger remedies for serious non-payment:

  • Suspension (Sub-Clause 16.1): if the Employer fails to pay in accordance with 14.7, the contractor may suspend work or slow the rate of progress after giving at least 21 days' Notice.
  • Termination (Sub-Clause 16.2): if the contractor does not receive the amount due within 42 days after the 14.7 payment period expires, it may be entitled to terminate the contract.

Both steps are serious and the Notice requirements are strict. Take contractual or legal advice before using them.

Frequently asked questions

Does the contractor need to submit a claim notice for late payment interest?

Under the Red Book 2017, the contractor is entitled to financing charges without a formal claim notice or certification. In practice, include the amount and calculation in the next Statement so the Engineer can certify it.

When do financing charges start if the IPC was issued late?

From the payment date under Clause 14.7. Sub-Clause 14.8 says the period starts on that date irrespective of when the Interim Payment Certificate was issued.

Are financing charges simple or compound interest?

Compound. FIDIC states the charges are compounded monthly on the amount unpaid.

Conclusion

Clause 14.8 turns late payment into a cost for the Employer. Calculate the charges accurately, claim them in every Statement while payment is late, and keep a clear record of due dates and receipt dates. Next in this series: how retention money is released under Clause 14.9.

For practical training on payment applications, certificates and claims, see Advanced Quantity Surveying: Payments under FIDIC and NEC Contracts.