The Final Statement under FIDIC Clause 14.11: Closing the Account

Asad Ali

Wed, 25 Nov 2026

The Final Statement under FIDIC Clause 14.11: Closing the Account

FIDIC contracts

The Final Statement under FIDIC Clause 14.11: closing the account

After the Performance Certificate, the contractor has 56 days to submit a draft final Statement. Here is how the draft, agreed and partially agreed statements work, and how the account is finally closed

The Final Statement is where a FIDIC contract's money story ends. It updates the Statement at completion once the defects period is over, and it leads to the Final Payment Certificate. Get it right and the account closes cleanly. Get it wrong and the contractor can lose money it was entitled to.

This article follows the FIDIC Red Book 2017 (second edition), which splits the clause into two parts: 14.11.1 Draft Final Statement and 14.11.2 Agreed Final Statement.

14.11.1: the draft final Statement

Within 56 days after the issue of the Performance Certificate, the contractor must submit a draft final Statement to the Engineer. It must be in the same form as the monthly Statements under Clause 14.3 and show, in detail and with supporting documents:

  1. the value of all work done in accordance with the contract;
  2. any further sums the contractor considers due at the date of the Performance Certificate; and
  3. an estimate of any other amounts the contractor considers have or will become due after the Performance Certificate, shown separately. These include claims, matters referred to the DAAB and any arbitration.

If the Engineer disagrees with or cannot verify any part of the draft, it must promptly give the contractor a Notice. The contractor then provides the further information the Engineer reasonably asks for, and the two agree any changes to the draft.

14.11.2: agreed and partially agreed Final Statements

What happens next depends on whether anything is still in dispute:

SituationWhat the contractor submitsWhat follows
Everything agreed, no estimated amountsThe Final Statement, as agreedDischarge (14.12), then the Final Payment Certificate (14.13)
Some amounts disputed or still estimatedA Partially Agreed Final Statement, with the disputed parts identified separatelyThe agreed part is certified and paid; the rest goes through the dispute process in Clause 21

The partially agreed route is one of the useful improvements in the 2017 edition. A few unresolved claims no longer hold up payment of everything that is agreed. Under Clause 14.7, the certificate for a Partially Agreed Final Statement is payable within 28 days after the Employer receives it, unless the Contract Data says otherwise.

The discharge and the Final Payment Certificate

With the Final Statement, the contractor submits a discharge under Sub-Clause 14.12, confirming that the total of the Final Statement is the full and final settlement of all money due under the contract. The discharge may state that it only takes effect once the contractor has received the outstanding balance and the return of its Performance Security. Use that wording: it protects you if payment never arrives.

The Engineer then issues the Final Payment Certificate under Sub-Clause 14.13, and the Employer pays within 56 days after receiving it.

If the contractor does not submit a draft final Statement in time, the Engineer can ask it to do so. If it still fails to submit, the Engineer may issue a Final Payment Certificate for the amount it fairly considers due. That is rarely good news for the contractor.

The close-out timeline at a glance

EventNext stepPeriod
Taking-Over CertificateStatement at completion (14.10)84 days
Latest DNP expiresPerformance Certificate (11.9)28 days
Performance Certificate issuedDraft final Statement (14.11.1)56 days
Final Payment Certificate received by EmployerPayment (14.7)56 days

Defaults under the FIDIC Red Book 2017 General Conditions. Check your Contract Data and Particular Conditions.

Practical tips for the quantity surveyor

  • Build the Final Statement from the Statement at completion. Update every line, close the agreed items and re-estimate the open ones.
  • Include every open matter. Clause 14.14 can bar matters left out of the Final Statement.
  • Make the discharge conditional on receiving the balance and the Performance Security, as the clause allows.
  • Use the partially agreed route rather than letting one dispute delay the whole final payment.
  • Close out subcontracts in step so that your own final accounts with subcontractors do not run ahead of the main contract.

Frequently asked questions

When is the draft final Statement due under FIDIC 2017?

Within 56 days after the issue of the Performance Certificate.

What is a Partially Agreed Final Statement?

A Final Statement covering the amounts the contractor and Engineer have agreed, with the disputed or estimated amounts identified separately. The agreed part can be certified and paid while the rest is resolved through the dispute procedure.

What is the discharge under Clause 14.12?

A written confirmation from the contractor that the Final Statement total is the full and final settlement of all money due. It can be made conditional on receiving the outstanding balance and the Performance Security.

Conclusion

The Final Statement is the contractor's last word on money. Prepare it from a well-kept register, include every open matter, make the discharge conditional and use the partially agreed route when you need it. That completes this series on FIDIC payment, from the advance payment in Clause 14.2 to the final account.

To practise these steps on real project documents, see Advanced Quantity Surveying: Payments under FIDIC and NEC Contracts.