Calculate excavation volume for trenches, pits and road formations, the loose volume after bulking, the number of truckloads to cart away, and the backfill you need.

Bank, loose and compacted volume

Bank volume is the volume of soil in the ground before digging: length × width × depth. This is what you measure in a BOQ.

Loose volume is larger, because excavated soil bulks up. Loose volume = bank volume × (1 + bulking factor). Use it to plan haulage and disposal.

Compacted volume is smaller than loose volume, so allow extra material when ordering backfill.

Worked example

A trench 20 m long, 1.2 m wide and 1.5 m deep is 36 m³ bank volume. In common earth with 25 per cent bulking, that becomes 45 m³ loose, or 3 loads in 15 m³ trucks.

Frequently asked questions

Is excavation measured as bank or loose volume?

Bank volume. Measurement methods such as CESMM and POMI measure excavation net, in place. Bulking, working space and disposal are dealt with in the rates or as separate items.