Calculate the concrete volume for slabs, beams, footings and round columns, then see how many cement bags and how much sand and aggregate you need for a site-mixed nominal mix.

How concrete volume is calculated

Rectangular elements (slabs, beams, footings): volume = length × width × thickness. A 5 m × 4 m slab, 150 mm thick, is 5 × 4 × 0.15 = 3.0 m³.

Round columns and piles: volume = π × diameter² ÷ 4 × height. A 450 mm diameter column, 3 m high, is 3.1416 × 0.45² ÷ 4 × 3 = 0.477 m³.

Add a wastage allowance, typically 3 to 5 per cent for ready-mix and more for hand mixing, then round up to whole truckloads when ordering.

Cement, sand and aggregate

For a site-mixed nominal mix, the calculator uses the dry volume method. Dry volume = wet volume × 1.54, which allows for voids and shrinkage. The dry volume is split by the mix ratio, and cement is converted to 50 kg bags at 0.0347 m³ per bag.

Frequently asked questions

How many bags of cement are in 1 m³ of concrete?

For a 1 : 2 : 4 mix, about 6.4 bags of 50 kg (around 320 kg). For 1 : 1.5 : 3, about 8 bags.

Should I measure concrete with or without wastage in a BOQ?

Measure net volumes in the BOQ. Wastage is the contractor’s risk and belongs in the rate, not the quantity.

Want to measure and price these items properly? Our practical courses show you how to take off quantities from real drawings and build a full BOQ: Road and Infrastructure Quantity Surveying, Bridge Pier Bar Bending Schedule (free) and all courses.